Media Centre
Interim Management Statement incorporating a production statement for the three months to 31 March 2010
Highlights:
- Ferrochrome (FeCr) production of 54,394 tonnes (t) for the quarter to 31 March 2010, up 48% on the prior year comparative quarter but down 6% on the previous quarter
- Sales of 64,063t for the quarter, up 76% on the prior year comparative quarter and up 85% on the previous quarter. Sales include 15,735t that is subject to pricing revisions based on subsequent benchmark pricing
- Inventory of 22,748t at 31 March 2010 (32,504t as at 31 December 2009)
- Electricity co-generation plant is on schedule and on budget for commissioning during the second half of calendar 2010
- UG2 ore supply agreement concluded with Anglo Platinum which will significantly reduce input costs and extend Lesedi life of mine
- Net borrowings of ZAR26 million as at 31 March 2010, principally due to increased working capital requirements (net cash of ZAR248 million as at 31 December 2009)
- European benchmark FeCr price increased from US$1.01 per pound in the first quarter of 2010 to US$1.36 per pound in the second quarter of 2010
| Ferrochrome | Three months to 31 March 2010 (tonnes) |
Three months to 31 December 2009 (tonnes) |
Three months to 31 March 2009 (tonnes) |
|---|---|---|---|
| Production tonnes | 54,394 | 57,942 | 36,773 |
| Sales tonnes | 64,063 | 34,553 | 36,383 |
| Stock at period end | 22,748 | 32,504 | 9,752 |
Commenting on the operational update, Chief Executive David
Kovarsky said:
“Stable and improving market conditions resulted in a healthy
price increase and good sales growth during the quarter. While
production was less than the previous quarter due to variability in
the grade of bought in ore feed, we expect these issues to be
resolved as mining operations ramp up and for sales and production
tonnages to be in line with management forecasts. The Company
remains confident that IFL is well placed to take advantage of the
continuing improvement in market conditions.”
Ferrochrome Market Conditions
Reflecting global stainless steel production growth, the European
benchmark ferrochrome price increased by US$0.35 per pound from
US$1.01 per pound in the first quarter of 2010 to US$1.36 per pound
in the second quarter.
The strong South African Rand continues to impact the Company, but Management are working to control those costs which it can influence, through innovations and measures such as the co-generation plant and the UG2 ore off-take agreement with Anglo Platinum.
Production
Production for the quarter (54,394t) decreased by 6% compared with
the previous quarter (57,942t). The lower production was
principally due to inconsistencies in the grade of bought in ore
feed while underground mining operations are ramped up. Over the
last two quarters, IFL has focussed on the development of the
underground mine to ensure long term sustainability and the
provision of high grade ore. As a result, the output from the mine
has declined in the short term. Increasing mine production and the
creation of larger stockpiles of bought in ore allowing for
improved blending and better ore feed consistency, will result in
an improvement of production by July 2010.
Sales
Sales for the quarter to March (64,063t) increased by 85% compared
with the previous quarter (34,553t). This included 15,735t sold but
which still bears pricing exposure; final pricing for these
tonnages will be fixed based on the benchmark price for the quarter
in which it is consumed by the customer. It is expected that about
70% will be consumed in the second quarter of 2010 at the higher
benchmark price of US$1.36 and the balance in the subsequent
quarter, giving IFM the benefit of both having reduced its
inventory and providing pricing upside.
Inventory
As announced in February 2010, the Company increased ferrochrome
stock levels to higher than the normal level of one month’s
production in order to take advantage of the then expected increase
in ferrochrome prices in the second quarter of 2010. The reduced
inventory level of 22,748t at the end of March 2010, from 32,504t
at the end of December 2009, reflects 15,735t of sales with ongoing
pricing exposure as described above held as a debtor balance at Q1
pricing with an anticipated price adjustment to be accounted for in
Q2 and Q3 of 2010.
UG2 Ore Supply
As announced in February 2010, the Company concluded a UG2 ore
supply agreement with Rustenburg Platinum Mines Limited
(“RPM”), a subsidiary of Anglo Platinum Limited. Under
the agreement IFL will pay approximately R150m for a chrome
re-treatment plant (“CRP”) to extract chrome
concentrate from RPM’s UG2 concentrator tailings. The
contract has a 10 year life commencing on the construction start
date and entitles IFL to 15,000t per month concentrate (about 30%
of IFL’s beneficiated ore requirements) from the
commissioning date at an effective cost per tonne significantly
below underground mining cost. Construction is expected to start in
June 2010 with commissioning in July 2011. The project is to be
funded using existing cash facilities.
Capital expenditure
Capital expenditure budgeted for the remainder of the financial
year is ZAR218 million which includes ZAR134 million for the
electricity co-generation plant, ZAR30 million for mine development
and ZAR 15 million for the metal recovery plant, in line with
previous announcements.
Cash balance
As at 31 March 2010, the Company’s net borrowings were ZAR26
million, against net cash of ZAR248 million at 31 December 2009.
The decrease of ZAR274 million was principally due to increased
working capital (mostly trade receivables) of ZAR160m and planned
capital expenditure of ZAR83m, principally on our co-generation
plant and mine development. The Company has a working capital
facility of ZAR500m and expects to generate significant operating
cash inflows during the quarter ending June 2010, under current
market conditions.
Outlook
The demand for ferrochrome has increased over the quarter with
corresponding improvement in stainless steel demand, as is
reflected in the current premium in the spot ferrochrome price over
the contract price. IFL expects this trend to continue as demand
from the USA and Europe continues to improve.
Other than as detailed above in this Interim Management Statement, there have been no material events or transactions in the period from 1 January 2010 to 27 April 2010.
- ENDS -
For further information please visit www.ifml.com or contact:
| International Ferro Metals
Limited David Kovarsky, Chief Executive Officer |
+27 (0) 82 650 1192 |
| Brunswick Group Carole Cable / Fiona Mulcahy |
+44 (0) 20 7404 5959 |
| Numis Securities Limited John Harrison / Stuart Skinner |
+44 (0) 20 7260 1000 |
About International Ferro Metals:
International Ferro Metals produces ferrochrome, the essential
ingredient in stainless steel, from its integrated chromite mine
and ferrochrome processing operations in South Africa.
International Ferro Metals is listed on the London Stock Exchange
under the symbol IFL.
Forward Looking Statements
This announcement contains certain forward looking statements which
by nature, contain risk and uncertainty because they relate to
future events and depend on circumstances that occur in the future.
There are a number of factors that could cause actual results or
developments to differ materially from those expressed or implied
by these forward looking statements.
« Back


